Approval items

50

Votes, budgets, contracts, grants, bonds

Stated approval dollars

$834.57M

21 items report an amount

Source records

100%

Real public records · every row links to its source

Recent approvals

ApprovalBudget

Action on the Award of a Public Works Contract for the Northern Receiving Station to Kifer Receiving Station 115 Kilovolt Transmission Line Project to Outsource Utility Contractor, LLC, for a Not-to-Exceed Amount of $31,172,792, Inclusive of a 20% Contingency (Contract No. 2455), and Related Budget Amendment

ApprovalContract award

Action on Agreements with ASF Electrical, Inc., Bear Electrical Solutions, LLC, and Cupertino Electric, Inc. for On-Call Electrical Maintenance and Repair Services at Levi’s Stadium, Limiting Authorization to Spend to a Total Aggregate Not-to-Exceed Amount of $1,506,408, Inclusive of All Option Years and Contingency Across All Three Agreements, and Delegated Authority for Future Amendments (Deferred from June 23, 2026)

ApprovalContract award

Action on Agreements with Devcon Construction, Inc., SC Builders, Inc., and Rudolph Commercial Interiors, Inc. for On-Call General Contractor Services at Levi’s Stadium, Limiting Authorization to Spend to a Total Aggregate Not-to-Exceed Amount of $1,506,408, Inclusive of All Contract Years and Contingency, Across All Three Agreements, and Delegated Authority for Future Amendments

ApprovalContract award

Action on Agreements with ACCO Engineered Systems, Inc., Mesa Energy Systems, Inc., and Silicon Valley Mechanical, Inc. for Mechanical and Plumbing Maintenance and Repair Services at Levi’s Stadium, Limiting Authorization to Spend to a Total Not-To-Exceed Amount of $1,506,408, Inclusive of All Contract and Option Years and Contingency, Across All Three Agreements, and Delegated Authority for Future Amendments

ApprovalContract award

Action on Agreements with ASF Electrical, Inc., Bear Electrical Solutions, LLC, and Cupertino Electric, Inc. for On-Call Electrical Maintenance and Repair Services at Levi’s Stadium, Limiting Authorization to Spend to a Total Aggregate Not-to-Exceed Amount of $1,506,408, Inclusive of All Option Years and Contingency Across All Three Agreements, and Delegated Authority for Future Amendments

ApprovalBudget

Action to Authorize the City Manager to Negotiate and Execute Amendments to the Agreement with Tucker Construction, Inc. for Encampment Cleanup Services to Exercise Option Years and to Increase the Total Not-to-Exceed Maximum Compensation and Approve the Related Budget Amendment

not disclosedTucker Construction, Inc
webapi.legistar.com/v1/santaclara/events/4883/e…
ApprovalBudget

Action on a Change Order to the Agreement with Jones Sign Co. Inc. to Include Extended Warranty for the Levi's Naming Rights Signage Refurbishment/Replacement CapEx Project at Levi’s Stadium, Budget Amendment in the Amount of $256,942, and Delegated Authority for Final Extended Warranty Amount

ApprovalBudget

Action to Authorize the City Manager to Negotiate and Execute an Agreement with Lyngsoe Systems, Inc. for an Automated Materials Handling System and Related Services, Authorize the Use of City Public Works Forces at the Northside Branch Library for System Installation Improvements, and Approve Related Budget Amendments

not disclosedLyngsoe Systems, Inc
webapi.legistar.com/v1/santaclara/events/4882/e…
ApprovalBudget

Action on an Agreement with South San Joaquin County Fire Authority for Municipal Hazardous Materials Response Services with a Projected Cost of $150,000 for FIFA World Cup and Approve Related Budget Amendment; Action on a Resolution Delegating Authority to the City Manager to Negotiate and Execute Future Municipal Hazardous Materials Response Services Agreements with Public Safety Agencies for Supplemental HazMat Response Services

ApprovalContract award

Action on Amendment No. 1 to Agreements with C2R Engineering, Inc., Golden Bay Construction, Inc., O’Grady Paving, Inc., A Teichert & Son, Inc., and West Valley Construction Company, Inc. for As-Needed Asphalt Repair Services to Remove the Annual Compensation Limit Subject to the Previously Authorized Maximum Amount of $10,400,000

ApprovalBudget

Authorize the City Manager to execute the 2026-2029 Memorandum of Understanding Between the City of Santa Clara and the Santa Clara Firefighters, International Association of Firefighters, Local 1171 (Unit 1), Approve a Corresponding Update to the Unit 1 Classified Salary Plan, and Approve Related Budget Amendment

ApprovalContract award

Action to Authorize the City Manager to Execute Amendment No. 2 to the Software License and Support Agreement with Siemens Industry Inc., for the EnergyIP Meter Data Management System for a Total Not-to-Exceed Compensation of $1,543,419, and Ratify Previous Payments Exceeding City Council Authorization